Direct materials variance is calculated as the difference between actual cost and standard cost. If actual cost is $150,000 and standard cost is $152,000, what is the variance?

Maximize your accounting skills with our Accounting SmartBook Test. Master concepts through flashcards and multiple choice questions, complete with hints and explanations. Ace your exam!

Multiple Choice

Direct materials variance is calculated as the difference between actual cost and standard cost. If actual cost is $150,000 and standard cost is $152,000, what is the variance?

Explanation:
Direct materials variance is found by subtracting the standard cost from the actual cost. Here, 150,000 − 152,000 = −2,000. A negative result means actual costs were lower than planned, which is favorable. So the variance is a $2,000 favorable difference.

Direct materials variance is found by subtracting the standard cost from the actual cost. Here, 150,000 − 152,000 = −2,000. A negative result means actual costs were lower than planned, which is favorable. So the variance is a $2,000 favorable difference.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy